The image below is again the highlighted digester top head as mentioned in previous blogs. This time it is pictured with our platforms, piping, etc. which are being installed by our field crew.
The Miller Mechanical field crew continues to prepare this major piece of equipment that will eventually be lifted atop the digester. The significant amount of pre-planning for this job, along with all the pre-assembly work seen here, is the most cost effective way to minimize the shut down time and thus save this Louisiana pulp and paper facility a considerable amount of time and money.
As noted in earlier blog photos this digester top head was previously fabricated in our shop. Along with the top head, the piping and platforms were also constructed at Miller Mechanical in Glens Falls and shipped to the mill.